Background
The Gym Group is a large national chain of 24/7 gyms. We were contacted by the electrical contractor to carry out the supply and commission of the fire alarm system at their Holborn Circus branch. The original design contained a few sections that required amendments to ensure it was compliant with British Standards.
Challenges
- Fire alarm commission to be carried out before handover.
- Installer required technical support.
- Full O&M manuals and detailed zone drawing required before handover.
- Connection landlord required further visit due to landlord’s engineer making changes.
Solutions
- On time service delivery.
- Expert phone support delivered by our technical team.
- All manuals and drawings delivered on time.
- Additional visit accommodated before opening date.
Why We Excelled
We carried out the work on time to budget and ensured the installer had everything they required including full O&M manuals and an A3 framed zone chart to ensure the system remained compliant.
Our services
We can help you with the following:
What is your role?
Find the information you need, quickly. Just select your role below:
Contact us
Our office is open
Mon to Thu – 8.30 am to 5.30 pm
Fri – 8.30 am to 3 pm